- Is the hydraulics of the piping system being addreesed by the
designer during the piping layout. Ditto for accessibility, maintainability,
operability, economics and surveillability. The reason i ask is that
practice here at our plant is we dont for the hydraulics but we do for
constructability and accesibility.
- What is the rule of thumb practice by the pipng designer in the
industry to mitigate a wind-induced resonant vibration of large bore piping
supported at regular interval.. Im refering to a piping subjected to w ind
load above 20 MPH.
- How is the cased crossing sealed and how does one center the
piping inside the casing - for piping crossing roads.
- For utility piping, is it necessary to install a local indicator
(PI) and a drain valve on a utility station and is it also necessary to
cap/plugged or blind both ends of open piping whenever hose (or breakaway
spool) is disconnected?question is both for utility and process side.