The pdf file referred to below is all about pipe modeling. A field
checklist prior to commissioning or mechanical acceptance is normally
term as punchlist. Normally this is part of the project deliverables
prepared not by Owner but rather by the Contractor.
The norsok site may hve something on this. If not email me and I'll send you a copy of our commissioning manual pertaining to Piping (if i still have it - not sure)Normally this activity fall unders the responsibility of your QC/QA (local law may require Inspector signoff) and not Operation.