Piping spool number and isometric break

From: <l_c_y1999>
Date: Wed Oct 20 2004 - 01:15:00 EDT


Dear member,

Have you ever experienced such probelem like: Isometric has to be broken up (It's a common problem now because Cad software been used widely, how much informaion can be put into one iso is pretty much out of control of human being.) but the inter-iso weld does not need to be a field weld (Shop weld saves some bucks).

And the most Spool ID naming system (sometime called Mark peice No.) consist isometric mumber (i.e 52P122-SHT1-01, 02...), So under all these circumstances I get 2 Spool IDs even though I want the interiso  weld to be done in shop.

Is this a probelem at all? I mean maybe the shop people wounld be confused and they will fab these two spool and weld then together then ship it to site with 2 SPOOL TAG No. with it?

Or the shop people do get confused?

What's your onpin on this?

Cheers

Robert Liu Received on Wed Oct 20 01:15:00 2004