I've heard (admittedly apocryphal) stories where the erection contractor hires an outside firm to create 2D drawings from 3D models in order to simplify things for construction.
Paul
C.Y L wrote:
> If a change on iso is needed then a FCN (field change notice) will be sent
back to our office along with a marked ISO (red line drawing), then we'll rev-up
the iso and update the model.
>
> Paul Bowers <pbowers@pipingdesign.com> wrote:
> C.Y L wrote:
>
>>In my company (EPC), piping GAs are not required, iso and 3d model are the
only deliverables. They will install the piping simply by using the iso and the
3d model.
>
> How are the inevitable design changes (during erection) tracked? Does
> the construction crew have their own 3D model that they can
> mark-up/modify according to field changes?