Hi all
In pump selection procedure in sewgae, I know that the recommended frequency
for pump operation is 6 times in hour also I have calculated sump volume to be
sure about 30 min retention time at maximum and I chose 4 pumps to pump 570 l/s
sewage and Head is 4.2 m.( I chose ITT Flyght 3125 CP/CT/CS)
My question is how can I find that this pump is apprpriate for my job, will it
starts 6 times in hour? retention time will be 30 min with my pumps? how can I
answer these question?
appreciate your contribution.
Omid