Re: Dimensioned Isometrics

From: <Paul>
Date: Fri Apr 15 2005 - 00:20:00 EDT


Thanks, Siva.

I assume that means (generally, since there are the other factors you mentioned that can vary) that butt welds over 20" diameter require multiple shifts. Can a partially-completed butt weld be left "overnight" and be continued the next day?

I'm referring to field welding, common Sch. 40 carbon steel.

Interesting that you mention climatic conditions. Some facilities have ambient construction temperatures that are lower than the usual -20 degrees F.

Paul

B.Sivasubramanian wrote:
>
> Dear Paul,
>
> The productivity of the Welds in Piping Works is a subject it self. The
production rate depends on the following factors
>
> 1) Whether the Weld is done in Fab Shop or Field
> 2) If in field whether it is Unit Piping or on Racks or on Pipes
> 3) MOC
> 4) Thickness of the Pipes (Schedule)
> 5) Pre weld / Post Weld heat treatment requirements
> 6) Welder's skill
> 7) Electrode Diameter used
> 8) Current used for Welding
> 9) Type of Welding Process (Manual / Semi Automatic / Orbittal etc)
> 10) Climatic Conditions
>
> etc.
>
> Just to give a guideline, if the work is in a typical hydrocarbon facility on
an average (say in a plant where the total quantum of works is 400,000 ID) you may consider 20Inch Dia per Welder Day ( 1 Welder Day = 8 hours of Work) Received on Fri Apr 15 00:20:00 2005