The Isometric can be hand-marked up with the changes
in "red", which forms the as-built mark up to update
the 3D model.
Sajit
--- Paul Bowers <pbowers@pipingdesign.com> wrote:
> In my company (EPC), piping GAs are not required,
iso and 3d model are the only deliverables. They will
install the piping simply by using the iso and the 3d
model.
How are the inevitable design changes (during
erection) tracked? Does
the construction crew have their own 3D model that
they can
mark-up/modify according to field changes?
As-builts seem to be gaining importance with the whole
plant life cycle
solution.
Paul
To visit your group on the web, go to: <a href="http://groups.yahoo.com/group/PipingDesign/">http://groups.yahoo.com/group/PipingDesign/</a>
To unsubscribe from this group, send an email to: <a href="/group/PipingDesign/post?postID=JnSz4Uj7zOE9VAfNoSY7DADsdJ4vlzdT9pBcBD2Pg3m_ypxpqKbX1hfkWctNXL8jDbBgud6DPTzoVBOWDeceB7ipjFtC0U5VvebhaWFBtBtUgLU">PipingDesign-unsubscribe@yahoogroups.com</a>
Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.
Send instant messages to your online friends <a href="http://uk.messenger.yahoo.com">http://uk.messenger.yahoo.com</a> Received on Fri Apr 22 02:39:00 2005
This archive was generated by hypermail 2.1.8 : Tue Mar 04 2008 - 11:40:41 EST