I have to install a PSV at elevation of 2 ft from grade level on a skid. Flare header runs at an elevation of 20 ft from grade. Discharge of the PSV to be connected with flare header. Now there is chance of liquid accumulation in the vertical portion of PSV discharge pipe.Liquid accumulation is allowed in the discharge piping of PSV and BDV?
If there is not possible to avoid riser pipe then what is its remedy to overcome liquid accumulation.
Thanks in advance.
Regards,