Hi Satish
Most of the points have been detailed by Paul in his Mail except one which
is very important is finalizing the critical piping for a given project
along with the layout..This become sometimes mandatory and essential since
the given area by a client for particular projects requires certain
adjustment which is better to be thought about initially then later.Usually
all critical piping is finalized along
with the layout with consultation with process and mechanical group.
In short both layout and stress analysis go hand in hand
Regards
Giridhar
Chennai
India
***********************Disclaimer********************************** The contents
of this E-mail (including the contents of the enclosure/(s)or attachment/(s) if
any) are privileged and confidential material of ENGINEERS INDIA LIMITED (EIL)
and should not be disclosed to, used by or copied in any manner by anyone other
than the intended addressee/(s). If this E-mail (including the enclosure/(s) or
attachment/(s)if any ) has been received in error, please advise the sender
immediately and delete it from your system.
***********************Disclaimer**********************************
Received on Sun Nov 20 22:48:00 2005
This archive was generated by hypermail 2.1.8 : Tue Mar 04 2008 - 11:40:45 EST