RE: ( Large Chilled) Water Network Design

From: <Conner>
Date: Fri Jan 27 2006 - 08:55:00 EST


Geoff,

Thanks for your comments. While I sometimes wonder about plastic pipe marketing claims (at least as they relate to water or sewer pipes etc. above service line size, let me just say that even if they were correct for any specific locale/application I'm not sure what that should mean to an engineer. Further to what I mentioned in my long post (for Paul's "hurt brain" condition I plead guilty), and then your specific mention of plastic pipe work in the UK, I did happen to see recently (I suspect as a possible result of at least some level of same) some folks there are apparently now grappling with some issues apparently related to the use of plastic pipes as mentioned at <a href="http://www.bhrgroup.co.uk/bhrsoln/stratech/pipepermeation.htm">http://www.bhrgroup.co.uk/bhrsoln/stratech/pipepermeation.htm</a> that leads off,

"...New information on the performance of polyethylene (PE) and polyvinyl chloride (PVC) water pipes and gaskets in hydrocarbon contaminated soils is urgently needed to help Utilities determine when the integrity of these assets may be compromised. The UK government wants to see 30% of future building projects on brownfield sites - but such sites frequently bring exposure to contaminates. There is a growing need for better information on the long-term behaviour of PE and PVC pipes when exposed to such contaminates..."

I wonder if the "30%" of construction to be in "brownfield sites" figure stated here is a factor (perhaps along with some unintended problems?) in the "urgency" expressed? In this regard, I have noticed that some regulatory agencies at least in the USA are even now taking it appears some pro-active, educating stances concerning these sorts of issues (e.g. see <a href="http://deq.mt.gov/LUST/TechGuidDocs/Techguid16.pdf">http://deq.mt.gov/LUST/TechGuidDocs/Techguid16.pdf</a> etc.)

Perhaps not unlike other sort of legacy issues mentioned in my post (third-party damage etc.), it thus appears at least some of our friends in the UK are apparently trying to deal somehow with this possibly very difficult issue that is also the result of increasing development/by-products of the Industrial/Hydrocarbon Age etc. (and also the "urgency" perhaps indicative in general of the type of issues I mentioned in some cases that at least in the past have not always been considered upfront?).

I am not familiar with "hot dip galvanized" in the context of ductile iron piping, but I am aware that some European manufacturers have promoted for many years zinc coating systems (in accordance with ISO 8179) as well as other specialty coating systems. My company furnishes pipes per ISO 2531 and with external coating per ISO 8179 on international projects when same is specified.

Randy Conner - ACIPCO

"Some powerful forces in the history of the world have been fueled by combined effects of ignorance and inertia."

-----Original Message-----
From: <a href="/group/PipingDesign/post?postID=7TV0qgqe5IjH_TmnJfwMPNqLbos76_6AikZLI44Vbc9zH1Yi6n_ygiNfa3ftxTo3AbdM11fa8TP31CcEaGygyFj1">PipingDesign@yahoogroups.com</a>
[mailto:PipingDesign@yahoogroups.com]On Behalf Of Geoff Stone DD&D
Australia
Sent: Tuesday, January 17, 2006 7:26 PM
To: <a href="/group/PipingDesign/post?postID=7TV0qgqe5IjH_TmnJfwMPNqLbos76_6AikZLI44Vbc9zH1Yi6n_ygiNfa3ftxTo3AbdM11fa8TP31CcEaGygyFj1">PipingDesign@yahoogroups.com</a> Subject: RE: [PipingDesign]( Large Chilled) Water Network Design

Randy,

   I always enjoy reading your commonsense factual commnets from the other side of an argument. I agree plastic pipe materials are not the answer to every application neither are they to be dismissed.

   The problems associated with buried pipelines in the WAE, I have been associated with, are that they are 3m below ground, in reclaimed land, that are subjected to sea water influx. GRP has had some mixed success there but beciuse of its low strain tolerance requires more intensive design and construction procedures. I attribute failures to the letting of design and construct contracts where the bottom line rules the so called engineering. Standards such as ISO 14692 and BS7199 are not enforced. Rather manufacturers own standards are employed. Once buried and the contractor has pulled off shore, who cares. There have been some spectacular failures over the years.

   In the UK the water and wastewater market is dominated (90%) by thermoplastics. DICL is used for high pressure rising mains only and then I am told it is hot dip galvanised. Larger mains are in steel. I am sure that this is an economic choice where the lower pressure applications can use thermoplastics.

   In Australia Tyco manufacture DICL to DN750 in Class 20 and 35 (20bar and 35 bar ratings). This is aimed at competing with thermoplastics. Our economics are different. The cost of transport from one manufacturing facility to the customer varies enormously.

   DICL is still used. Mild Steel Cement Lined (MSCL) is about 10% more expensive than DICL. Thermoplastics & GRP are price targetted depending upon factory loading, transport & customer history long before pressures are considered.

   The jury is till out on the celerity of buried thermoplastic pipelines. End constraints also modify the actual numbers. The effect of embedment and native soil has not been researched. If there is column separation and rejoining it hardly matters what material you use the extreme pressures will exceed Joukowsky predictions.

   All material properties are strain rate dependent. The normal stress strain graphs we learnt at college and university are generalisations. If the theory of explosions, impact loads and fracture machanics are studied impacts from waterhammer loads need to be considered in more depth. Materials are able to withstand higher stress levels than predicted by static analysis provided that they do not have faults such as weld defects, notches, cavities, delaminations etc.

   Even the attempts to link waterhammer pressure loads to structural (pipe) behaviour are fraught with danger. It is nighe impossible to replicate a physical model for waterhammer analysis in the same way as a structural pipe model. When the structural loads are applied either as static or time hisory effects on a modal analysis the effects are inconsistent. Pressures are applied at curved surfaces whereas structural loads are applied differently.

   The codes and standards are presented as compromises with conservative approaches to the design of systems. They must be tempered with field experience. The design is but one part of an installation. The code such as B31.3 covers, design, fabrication, examination, installation and testing. The code is also backed up with material standards and requirements for qualification. They are an intricate web of documents that cannot be grasped overnight or by reading a few emails. It takes decades to get abreast of them and keep up with the changes.

   Geoff

Design Detail and Development (a division of Blenray Pty Ltd)

Mail Address PO Box 1351 Castle Hill NSW 1765 Australia Tel Mob 0402 35 2313 Office 02 8850 2313 AH 02 8850 2324
We specialise in pipe network and waterhammer analysis, pipe stress analysis, the design of buried pipelines and thermoplastic pipe systems.

[Non-text portions of this message have been removed]



PipingOffice - Excel Spreadsheets for Piping Calculations <a href="http://www.pipingoffice.us/">http://www.pipingoffice.us/</a>

Main site: <a href="http://www.pipingdesign.com">http://www.pipingdesign.com</a>

Yahoo! Groups Links

_________Confidentiality Notice_______________________
This e-mail and any files transmitted with it is confidential and is intended solely for the use of the individual(s) or entity(ies) to whom this e-mail is addressed. If you are not the intended recipient or the person responsible for delivering the e-mail to the intended recipient, be advised that you have received this e-mail in error, and that any use, disclosure, dissemination, forwarding, printing, retention or copying of this e-mail is strictly prohibited. If you have received this e-mail in error, please immediately return this e-mail to the sender and delete the e-mail from your system. Thank you. Received on Fri Jan 27 08:55:00 2006

This archive was generated by hypermail 2.1.8 : Tue Mar 04 2008 - 11:40:46 EST