PIPELINE CONSTRUCTION
1.1 GENERAL
This section describes the main activities and processes involved in
constructing a large
diameter onshore pipeline.
1.2 PRINCIPLES OF PIPELINE CONSTRUCTION
A pipeline can be broken down into three basic elements where different forms
of pipeline
construction method are used. They are:
open cross-country areas, where the spread technique is used (ii)crossings, where specialist crews and civil engineering techniques are used
(iii)special sections such as built up urban areas, restricted working areas,
difficult
terrain sections and environmentally sensitive areas
1.3 SPREAD TECHNIQUE AS USED IN OPEN CROSSCOUNTRY
AREAS
The basic method of constructing steel, welded oil and gas onshore pipelines
in open cross-country areas is generally known as the spread technique. The
spread technique utilises the
principles of the production line system, but in the case of a pipeline the
product (the pipeline)
is static and the individual work force, (crews) move along the pipeline track
(right-of-
way/spread). The implementation of the spread technique is conditional on the
pipeline being
welded above ground in maximum possible continuous lengths between
obstructions/crossings
(which can extend to lengths in excess of 10 kilometres). These welded pipe
lengths are then
immediately installed into unsupported/unobstructed trenches gradually in one
continuous
length utilising multiple (three or more) mobile lifting tractors (side-booms)
in unison.
The breaks in the continuous main spread method of working result from the
location of
existing services, roads, railways, tracks, ditches, streams and river
crossings, and are also
dependent upon restricted working, time constraints and physical
features/obstructions. These
breaks in the main pipeline spread activities are undertaken by dedicated
specialist crews
utilising a variety of special construction techniques and are generally
undertaken after the main
pipeline sections have been installed.
The main pipeline spread installation is undertaken by dedicated crews
undertaking one
operation at a time commencing at one end of the pipeline and travelling forward
to the other
end at anything from 500m to 1,500m per day depending on the diameter of the
pipe, terrain,
soils, etc. There are a total of some 40 separate operations carried out in 7
main activity groups,
as described in Sections A.5.1 to A.5.7 inclusive. The programme of activities
and the start-up
of the crews is dependent on available resources and the risk of one crew having
an impact upon
the following activities.
Because a pipeline is a production line, it is essential that the time periods
between crews is
such that there is no risk of one crew causing stoppage or disruption on the
preceding or
subsequent crew. If the float between crews is not managed on a continuous
basis, with the
emphasis placed on the daily moving, then a concertina effect will result with
substantial
disruption and standby costs. Effectively, there can be up to a 4-week delay
between crews to
ensure that the concertina bunching effect of crews does not occur.
Consequently, there are in
the programme extended periods of time when there are no activities taking place
along large
sections of the pipeline route. The average time from start of ROW to
commencement of land
reinstatement is, typically, in the order of 10 to 15 weeks.
1.4
PRE-CONSTRUCTION ACTIVITIES
Pre-construction activities need to be carried out by the Installation
Contractor prior to the start
of the main pipeline installation activities. These activities include
finalising the pipeline route,
detailed design finalisation, mobilisation, notification of entry to landowners,
setting-up of pipe
yards and base camps, establishing temporary works requirements, setting-up of
geographic
positioning stations, design of land drainage in agricultural areas and
reinstatement works,
construction of temporary access roads, pre-environmental mitigation works, and
agreeing with
landowners any special requirements prior to entry onto their propertie s.
The Installation Contractor will carry out pre-entry surveys as-and-where
required so as to
record the condition of the land prior to the start of any work.
1.5 MAIN PIPELINE CONSTRUCTION ACTIVITIES
Once the pre-construction activities have been completed, then the main
construction works can
commence. Generally, operations are carried out in seven main activities groups,
as described in
the following sections:
1.5.1 Construction Activity Group 1 – Preparing Work Area
1.5.2 Construction Activity Group 2 – Layout Pipe and Weld above Ground 1.5.3 Construction Activity Group 3 – Excavate Trench and Installation of Pipe 1.5.4 Construction Activity Group 4 – Pipeline Crossings, Special Sections and Tie -Ins
1.5.5 Construction Activity Group 5 – Final Backfill and Reinstatement Works 1.5.6 Construction Activity Group 6 – Facilities and Pipeline Control 1.5.7 Construction Activity Group 7 – Testing and Commissioning
General details are shown in Figure 1.
1.5.1 Construction Activity Group 1 – preparing work area The pipeline operations consist of:
The setting-out crews are the first personnel from the construction contractor’s
workforce to
enter the site to commence the main construction activities. The setting out of
the works should
be scheduled to commence at least four weeks prior to the remainder of the
construction activity
group 1 activities. This work will be carried out with small four man crews
using GPS and
surveying instruments. Setting-out pegs will be placed at all boundaries,
changes in direction
and intermediate sightings on the proposed centre line and the extremities of
the working
easement.
In areas of open country where good and level access is available along the
pipeline route and it
is anticipated the rock or ground is of sufficient strength that it could impede
progress of the
trench excavation, then initial ground investigations works will be carried out
directly behind
the setting-out crew.
Part of the setting-out crew’s duties is to identify any existing services that
cross or are in close
proximity to the pipeline and supervise the trial hole crew. The trial hole crew
will hand
excavate to expose, identify and determine the exact location of all existing
services. This data
will be recorded and transferred to the engineers for incorporation into the final pipeline design.
2. Advanced archaeology major works
This applies to locations where there are substantial/concentrated archaeology
remains, which
could involve extensive excavations. Provided access is available or requires
minimal work
along the ROW from an established entry point, a separate advanced ROW and
topsoil/top
cover crew will be mobilised to enable the archaeology works to commence in
advance of the
mainline and be completed before front-end crews pass. The topsoil/top cover at
archaeology
locations will be stripped by back-actors to avoid any disturbance to the
stripped subsoil.
3. Right of Way/easement boundary demarcation – secondary ground investigation
option 1
This will commence after the setting-out. A crew of personnel and equipment
comprising
mainly large heavy tracked plant will form the right of way access onto the
land. The operations
will include the removal of all hedging for disposal off site, bridge or flume
pipe access across
field ditches, protectio n of existing services by protection mattresses,
re-grading of existing
ground contours to assist access, the erection of goalpost and safety signs at
overhead electric
power lines and telecommunication cables, the placement of hard standings as
required for car
parking and the blasting/removal and re-grading of rock areas or outcrops to
provide a level and
safe excavation line/running track along the entire pipeline route.
Additional crews will be provided to install offsite ROW accesses along the
pipeline route to
enable the ROW crew to gain access to the working areas, where access from the
public road is
not available or would cause a safety risk, or as a result of locked out
locations or environmental
concerns. Agreement with the landowners involved in any offsite access must be
finalised prior
to pipeline commencement.
Where temporary ROW fencing is required then additional crews will be required
to erect this
fencing to delineate the working area.
During the ROW and fencing operation it will be possible to undertake ground
investigation
works by the excavation of trial pits at 100 metre intervals to determine actual
ground substrata,
trench stability, ground water levels and seepage. These investigations,
however, can
only take place at this time on open areas where restrictions due to land use
(agricultural) and
environment do not exist.
4. Pre-construction terrain and ground stability (excluding dewatering)
At locations where there is a risk of ground movement that could result in
safety risks to the
construction activities and/or undermine the pipe during installation and the
period prior to final
reinstatement then permanent stability of the affected terrain needs to be
undertaken. This work
can be separated into two elements:
Removal of material such as the overburden at the top of ravines and the
removal of
loose material that could move during the installation works
Addition of material such as Bentonite, which is injected under pressure into
gravels
with high and fast water tables and deep mining areas to provide a protective
curtain
around the pipe. It also includes the adding (placement) of boulders/ground at
the toe of
steep gradients on forwarded and side slopes in the second element
5. Trench excavation in rock areas
In areas where rock is confirmed as such by the initial ground investigation
works then the
trench is excavated ahead of any pipe operations. This sequence of working is
undertaken to
ensure that the excavation of the trench cannot cause any damage to the pipe
and/or pipe coating
and provide an extended safe working width for the excavation crews allowing
double -sided
trench working by excavators/ breakers.
Following the review of the data from the initial ripper and trial hole surveys,
the ground will be
classified in ease of excavation into five groups defined by the method of
removal. These are (i)
utilising standard excavation, (ii) larger more powerful excavators (face
shovels converted to
back-actors), (iii) ripping/hydraulic hammer and excavation, (iv)
blasting/hydraulic hammer and
excavation and (v) rock trenchers (saw and blade). The finished trench should be
to the correct
depth and width to suite the pipe diameter, plus any bedding and pipe cover.
The trench should
also be in a straight line so that the pipe can la y central in the trench
without coming into
contact with the trench sides. All loose and jagged outcrops, which could come
in contact with
the pipe during lay operations, will be removed.
The excavation will commence with dedicated crews immediately following the ROW
operation. The forward progress will be dependent upon the ground strength,
grain structure,
terrain, access, method of removal and number of crews/equipment employed.
6. Pre-construction cut-off drains
All cut-off drainage works, which comprise the connection of existing drains to
a new header
pipe, will commence immediately after the right of way and fencing operations.
Cut-off drainage works will be undertaken at locations where there are existing concentrated
drainage schemes on agricult ural land and where agreement is reached with the
landowners
and/or occupiers to their installation. This work will be resourced taking
account of the scope of
work and the requirement to achieve pipeline installation progress of, say, 500
to 1,500 metres
per day along the pipeline route.
7. Topsoil strip -secondary ground investigation Option 2
Topsoil strip operations commences after cut-off drainage operations and is scheduled to allow
adequate time for completion of the drainage works in the event that
unforeseen obstacles or
circumstances are highlighted during the execution of the drainage installation
operations.
The topsoil operation consists of 1 crew with plant comprising up to 8
excavators/ bulldozers
removing the topsoil to its full depth (typically, = 300mm) and storing in a
single stack on the
opposite side of the easement to the trench excavation material. The topsoil
is stripped with 2 to
3 excavators along the easement boundary on the opposite side to the topsoil
stack area. This
provides a subsoil interface/cutting edge for the dozers to work from in pushing
the topsoil
across the easement.
In areas where topsoil removal is required then the ground investigation works
are undertaken
following the removal of the topsoil as this avoids any risk of topsoil
contamination with the
subsoil. The investigation works are as those detailed in the ROW section and
comprise the
excavation of trial pits at 100 metre centres to determine actual ground
sub-strata, trench
stability, ground water levels and seepage.
1.5.2 Construction Activity Group 2 – layout pipe and weld above ground
The pipeline operations consist of:
Prior to the start of any mechanical works the Contractor will issue for Client approval a full set
of mechanical procedures for bending, welding, x-ray and coating. These
procedures will
address how the Contractor intends to undertake the work in accordance with the
project
specifications detailing equipment and specific mandatory requirements. The
procedures,
particularly with regard to welding and x-ray will be sufficient to cover the
full ranges of the
various parameters characteristic of the project in terms of diameter, wall
thickness and
technique. Once the documented procedures are approved then full trials for each
element of the
works will be carried out, fully inspected and witnessed by the Client. The
welding will include
non-and full destructive testing to ensure that the procedure welds are
undertaken in strict
compliance with the contract requirements and fully comply with the minimum
strength,
hardness and quality requirements of the relevant specifications.
Once the procedures have been approved then the welders will be tested to ensure
that they can
comply with the requirements of the procedure welds. A register will be
maintained of the
welders employed on the project with the various welding techniques they are
approved to work
on.
2. Double-jointing
Double-jointing of the single approximately 12 metre long pipes into 24 metre
lengths will, if
considered economically viable by the project, be carried out in the pipe yards
prior to pipeline
stringing. Double -jointing permits the doubling of the welding progress with
the same basic
welding resources or allows the same production with a much smaller crew.
In considering double -joints due consideration needs to be given to the use of
specialist pipe
bogies for the moving of the 24 metre pipes, the capability of the local road
system to
accommodate the vehicles and the requirement for special road movement permits.
The double -
jointing can be placed on the easement but this results in additional cost due
to double handling
of the pipe and the need to continually move the double joint equipment, which
can offset any
savings from increased welding production.
3. Pipe stringing
The pipes and pre-formed bends will be scheduled to be delivered to, and stock
piled at, the
proposed pipeline pipe yards some 4 to 8 weeks in advance of stringing
operations. The pipe
supply should ensure that the various grades, wall thicknesses and coatings are
supplied in
sufficient and correct quantities to meet the programme.
Immediately following ROW or topsoil strip or excavation in rock areas, the pipe stringing
operations will commence, which involves laying the pipe lengths along the
easement length
using pipe trailers. A typical crew will consist of two cranes - one at the base
camp loading the
pipe trailers and the other on the pipeline easement off-loading the pipe
trailers.
In the event that ground conditions do not permit travel down the easement with
standard or
special heavy-duty pipe trailers then the pipes will be loaded on to tracked
pipe carriers at the
public roads or at a point where the change in ground conditions occurs and
permits the turning
of the wheeled pipe trailers.
4. Forming field bends (cold bending)
Once the pipe has been strung along the easement, engineers will follow to
determine the
location of all bends required in order that the pipeline can follow the
contours of the land and
the required line and level as detailed on the drawings. There are two types of
bends normally
used ie hot pre-formed or forged bends which are manufactured off site in a
factory and are to a
radius of 5 or 3 times the pipe diameter and cold bends which are to a radius of
40 times the
pipe diameter and are formed in the field.
A typical cold bending crew consists of a four-man team together with a bending
machine and a
side boom tractor. The bending machine is towed along the pipeline route by the
side boom and
includes “formers” consisting of 20 – 150 ton hydraulic rams, which bend the
pipe to the
required radius and angle. The side boom acts as a lifting device and has a
fixed jib attached to a
tracked dozer with a capability of lifting between 15 to 120 tons, dependent
upon the size of the
machine used.
The number of cold bends required depends on the route and contours of the
pipeline. Typically,
they can range from 1 pipe in 10 in developed regions to 1 pipe in 50 in open
country. The cold
bend angle that can be achieved ranges from maximum angles of 12 degrees (42”
pipe) to 40
degrees (12” pipe).
5. Welding of the linepipe
The welding of the pipeline will commence a few days after the cold bending
crew. The
welding crew will weld the pipeline in continuous lengths between features such
as roads,
watercourses, tracks, railways, services and other underground obstacles that
prevent the
linepipe being continuously installed in the trench.
There are primarily two methods of welding which are manual or automatic. As the
names
imply manual welding involves the welding of the pipe by welders and automatic
involves a
semi-automatic system. At present, and with the correct welding experience,
there is no
substantial difference in quality or production.
Automatic welding is used primarily for three main reasons:
Ensure welding quality
Increase/sustain a high daily production rate
Reduce the overall manpower requirements
Manual welding is used where:
A supply of experienced welders is readily availa ble
Difficult terrain, weather and site conditions exist Special sections and areas with a high percentage of tie -ins High production rates cannot be achieved
Both systems generally (although certain automatic systems can now do single
pass complete
welds) operate on a front-end/back-end principle. The front-end consists in a
manual operation
with, say, 3 separate welding stations placed on CAT D6 carriage consisting of a
HIAB for the
welding shelter (used in inclement weather or windy conditions), 4 welding
bullets and a
compressor. The welding stations work on 3 separate joints and complete one pass
before
moving on with the sequence being the bead (2 - 4 welders), immediately
followed by the hot
pass (2 – 3 welders) and then hot fill (2 welders). With the automatic process,
1 machine
deposits sufficient weld metal equivalent to the 3 manual passes. The weld is
allowed to cool
after the front-end passes and then sufficient welders working in pairs or
multiple automatic
machines follow on to fill and cap that day’s production.
The crew will achieve progress in the order of one weld approximately every 3 to 5 minutes or
up to 90 to 150 welds per day, which is equivalent to 1,000 to 1,500 metres of
linepipe on 12
metre pipes and up to twice that if double -jointed pipes are used.
6. Welding of fabrication pipework
As the mainline welding crew is set up for speed and any reduction in the speed
will increase
costs and could cause delays to following operations then any fabrications or
pipework
involving bends or difficult set-ups or welds that require more than the bead
before lowering off
(creating cracks) will be left out. These fabrications are welded together by
a small dedicated
crew who complete these welds prior to the field joint coating crew.
7. NDT inspection
All welds on the pipeline are generally subjected to inspection by radiography.
This is achieved
on the main pipeline by an internal x-ray tube travelling along the inside of
the pipe carrying out
x-rays at each weld for approximately 2 minutes per weld. On completion of the
x-ray the film
is taken to a dark room and processed in time for the results to be available
for inspection at the
end of the day or early the next day. Welds, which do not meet the required
acceptance criteria,
are either repaired or cut out and re-welded.
Experienced and qualified x-ray specialists undertake the radiography under
controlled
conditions. Before the operation is started, the section of pipeline is cordoned
off by marker tape
to stop entry by non x-ray personnel and audio/flashing warning alarms are
activated during all
times when the x-ray tube is energised. The x-ray personnel are on constant
surveillance to
ensure that the workforce and members of the public are aware of the x-ray
activities and only
authorised access is permitted.
Welds completed by semi-automatic welding processes are examined using
automatic ultrasonic
testing (AUT) techniques. This consists of an assembly that traverses the
circumference of each
completed weld in order to detect any defects. The results of each
ultrasonically inspected weld
are automatically recorded and are used to determine whether a weld repair is
required and if so
what type.
8. Weld rectification (repairs)
A weld rectification (repair) crew follows immediately behind the NDT inspection
activities to
either carry out repairs to or cut out any defective weld. On completion of all
repairs a further xray
is carried out on the weld to ensure that the finished weld conforms to the
standard required.
The x-ray of repair welds is usually carried out from the outside of the weld by
a two-man crew.
9. Field joint coating
The coating of the pipeline field joints to prevent corrosion starts a few days
after the welding.
This extended period is to allow for any repairs or cut-outs to be completed
without prejudicing
the coating crew’s operations.
1.5.3 Construction Activity Group 3 – excavate trench and installation of pipe
The pipeline activities consist of:
In areas other than rock, trench excavation commences a few days after the field
joint coating
operation. A typical trench excavation crew consists of 5 - 8 excavators working
in line. This
operation only excavates the length of open cut trench sufficient to install the
main line welded
pipe; it does not excavate any roads, ditches, services or obstacles. The number
of excavators
employed will be such that the amount of trench excavated in a single day
matches the rate of
progress of the welding crew. The spoil from the trench will be stored adjacent
to the trench on
the opposite side of the ROW from the topsoil stack.
The finished trench will be to the correct depth and width to suit the pipe
diameter, plus any
bedding and pipe cover. As far as possible, the trench should also be in a
straight line so that the
pipe can lay central in the trench without touching the trench sides. All loose
and jagged
outcrops, which could come into contact with the pipe during laying operations,
will be
removed.
2. Trench excavation archaeology watching brief
As part of normal good practice an archaeologist will be present during the main
trench
excavation undertaking a watching brief of the material being excavated. The
archaeologist will
have the authority (subject to safety constraints) to stop the trenching works
if he considers the
excavation has encountered a major archaeological find.
3. Finalise drainage design
In agricultural land, the Contractor will record the existing drainage system
actually intercepted
by the pipeline. The information will be reviewed taking account of the intended
proposals and
any final amendments to the system finalised at this stage following
discussion with the Owners
or Occupiers.
4. Pipe installation (lower and lay) – above ground tie-in sections
The linepipe will be positioned approximately 5 metres from the trench
centre-line and will be
installed into the open unobstructed trench utilising a number of side-booms.
This operation will
usually be carried out immediately following the excavation crew.
As the linepipe is being installed a coating crew will be present who will
holiday detect the pipe
to detect any damage to the pipe coating just prior to the pipe entering the
trench. Any holidays
(damage) detected will be repaired by a fast setting repair coating.
In areas of rock, the pipe installation will commence anything from 5 to 15 days
after the
welding crew.
If there are any above ground breaks in the mainline due to access openings
across the ROW,
expansion breaks or bend breaks, then these will be welded above ground, x-rayed
and coated
during the excavation and lowered-in as part of the mainline lower & lay
operation. This will
optimise the use of the side-booms within the lower & lay crew and reduce the
number of below
ground tie-ins.
5. Cross trench drainage connections
In agricultural land, the permanent reinstatement of the existing land drains to
be replaced
across the pipeline trench is carried out prior to the trench backfill
operations. The replacement
drains extend for a short distance into undisturbed ground.
On completion of inspection of the reinstatement works, the trench is backfilled
and compacted
in layers to the underside of the drain. This work is only undertaken in extreme
locations to
supplement the main pre- and post-drainage schemes
6. Installation of permanent cathodic protection system test posts
Either as part of the fabrication welding crew activities (if the location of
the CP test posts are
known) or as the pipe is being installed Cathodic Protection lugs are welded to
the pipe. These
lugs which can be 50mm square plate are welded on the pipeline using low
hydrogen welding
rods where test posts will be installed to check the ground/pipe to soil
potential. The test posts
are placed at about 1km distances along the pipeline and located at fixed
boundarie s such as
road crossings or other locations, which have relatively easy access. Cables are
attached to the
lugs the whole area coated, checked for holidays and the cables brought to
ground level during
backfilling and left. During the reinstatement activit ies the Cathodic
Protection test posts are
installed with the cable running up through a duct in the test post and tied
off. The test post is
then concreted into the ground directly above the pipeline.
7. Temporary cathodic protection system
As the pipeline may be buried for the full construction period before the
permanent Impressed
Current Cathodic Protection (CP) System is activated, then some form of
temporary system
needs to be installed prior to the backfilling of the pipe. The temporary
system, typically,
comprises a number of zinc anodes attached to the pipeline at regular
intervals. These are buried
parallel to and at a distance of, say, 3 metres from the pipe.
8. Backfill of the pipeline trench
Trench backfill starts immediately following the placement of the linepipe in
the trench and the
undertaking of a survey of the pipe levels by the engineers to confirm that the
required pipe
cover has been achieved. There is a requirement that the initial backfill around
the pipe and to
300mm above the crown be of loose and relatively fine particles, which can be
readily
compacted and do not damage the pipe coating. In areas of rock it will be
necessary to place the
pipe on a 150mm bed of similar material. In order to provide this material it
may be necessary
to import sand/soft material offsite, sieve the excavated material or crush the
excavated
material. The sieve and crusher equipment will be portable machines, which will
be transported
along the pipeline ROW.
The pipe is backfilled over the entire length except for, say, 30 metres at each
end of the
pipeline work section, which is left free to facilitate the tie -in to the
crossing/line break pipe
work.
1.5.4 Construction Activity Group 4 – pipeline crossings, special sections and tie-ins
The pipeline operations consist of:
The crossings are carried out by a number of different and dedicated crews
simultaneous with
the main trench excavation works and final tie -in to the main pipe installation
being carried out
by subsequent tie -in crews following completion of the crossings and main
pipeline installation
works. The crossings are undertaken by two distinct methods of construction
consisting of
either:
Open cut
No dig technique
There are various options to the two methods of working and the actual method
employed at
any given location will be dependent upon the ground conditions, pipe diameter,
local
environment, third party restrictions and the type of obstruction being crossed.
The extent of a crossing in design terms is normally defined from fixed
locations, which extends
either side of the crossing land take or boundary fencing. However, the length
of a crossing in
terms of construction includes the crossing plus any temporary works to
facilitate the
installation, the swan neck offsets to bring the pipe back to normal cover and
the tie -in pipes to
connect the crossing to the mainline.
A key aspect in the determination of the method of construction that will be
used at any crossing
will be the requirements of the regulatory authority/owner that has jurisdiction
over the
crossing. Part of the approval process with the regulating authority will be the
issue of detailed
plans and calculations of the design, which will be supported by fully detailed
construction
method statements.
Details of the various crossing methods are described herewith and are taken
in the order of ease
of construction and cost.
Open cut
Open cut is generally by far the most cost effective way of crossing obstacles
that cause breaks
in the mainline and is undertaken by crossing the obstruction by means of an
open excavation.
The trench excavation at the obstruction, whether it be a ditch, a road, a
railway, a river, or a
service is excavated for the full length of the crossing prior to the
installation of the pipe.
Accordingly, in order to minimise the time for which the crossing trench is
open, the welding,
NDT inspection and field joint coating of the section of pipe required for the
crossing is
completed in advance of excavating the trench. An open cut crossing can very
often be installed
in one working day and the road or ditch temporary reinstated sufficiently to
fulfil the function
for which it is required prior to the crew-leaving site for the day.
No-dig technique
At locations where open cut methods are impractical or not permitted for
whatever reason, then
no-dig techniques have to be implemented. No-dig techniques can be classified
into two main
groups - sleeve or ‘bare’ line pipe. The actual method that will be used is
determined by the
ground conditions, third party restrictions, length of crossing, diameter, and
design/safety
requirements.
The different options available for no-dig techniques are described briefl" Received on Sat Mar 17 11:52:00 2007
This archive was generated by hypermail 2.1.8 : Tue Mar 04 2008 - 11:40:49 EST