RE: 42 Hot Tap & Line Stop

From: <bruce.r.raymond@fluor.com>
Date: Wed Oct 10 2007 - 05:50:00 EDT


AJ - forgot to mention that there are pressure bleed / equalization fittings required (normally 2") as well -which can be independent extra hot tap fittings, or integrated into your main 42" main hot tap fittings. these connections are required to relieve pressure differential to allow hot tap fitting / machine / line stop setting / removal. If you have some upstream & downstream existing taps in your main line these could possibly be eliminated.

Bruce R. Raymond
Fluor



The information transmitted is intended only for the person or entity to which it is addressed and may contain proprietary, business-confidential and/or privileged material. If you are not the intended recipient of this message you are hereby notified that any use, review, retransmission, dissemination, distribution, reproduction or any action taken in reliance upon this message is prohibited. If you received this in error, please contact the sender and delete the material from any computer.

Any views expressed in this message are those of the individual sender and may not necessarily reflect the views of the company.


[Non-text portions of this message have been removed] Received on Wed Oct 10 05:50:00 2007