Re: minimum depth to be maintained for burried(underground) condensate pipeline.

From: <ashok>
Date: Fri Jan 18 2008 - 00:56:00 EST

Thanks

sviswan@technip.com wrote:
A metre depth from the TOP to grade is normal. The governing consideration should be the dia of the pipe, thickness, the max wheel load at the load crossing. There is one software called CROSSI, that I had seen, that did the loading check for road crossing. Your civil people would be able to help you with this.

Sajit

Save a tree...please don't print this e-mail unless you really need to.



Looking for last minute shopping deals? Find them fast with Yahoo! Search.

[Non-text portions of this message have been removed] Received on Fri Jan 18 00:56:00 2008