A metre depth from the TOP to grade is normal. The governing consideration
should be the dia of the pipe, thickness, the max wheel load at the load
crossing. There is one software called CROSSI, that I had seen, that did
the loading check for road crossing. Your civil people would be able to
help you with this.
Sajit