Piping Tie-Ins: The Basics
Making these connections is inevitable during plant expansion. Here are
a few ways to minimize costly disruption during this procedure
By: Peter Y. Burke, P.E., Day & Zimmermann International, Inc., Chester,
Virginia
Piping tie-ins are unavoidable in plants where expansion is a current or future factor. Steam, condensate, compressed air, dust collection, vacuum and process lines are just a few types of plant piping likely to be modified by tie-ins to increase capacity. Here are a few ways to minimize costly disruption of plant operation when tie-ins are inevitable.
-Plan and schedule New piping design should include allowances for
future expansion. This can be accommodated without major expense.
Consider the following:
-Increase design pipe sizes to the next larger diameter if velocity
limits permit.
-Provide caps or blind flanges at the end of a pipe run where a brief
tie-in outage can be tolerated.
-Provide valves with blind flanges when and where a future tie-in outage
cannot be tolerated.
-Provide adequate access and maintenance space for future connecting
piping.
Existing piping design may provide limited flexibility for future piping tie-in accommodations. However, take advantage of future scheduled outages and add piping flanges and valves where future tie-ins are inevitable. This will enable future construction to proceed without disrupting plant and process operations.
Documentation
The piping and instrumentation diagram (P&ID) is a useful means to
define piping tie-ins. The P&ID does not locate the tie-in physically.
However, it defines the functional relationship of the tie-in within the
piping system, which is the initial step in the design process.
Establish a numbering system for tie-ins, i.e., "T-XXX," which can be
used as a reference on design documents until the project is completed.
An indication of "new" and "existing" piping also provides clarity.
A tie-in list can also be useful for estimating the cost of construction
and for scheduling work well in advance of the actual piping design
activity. Often, the list will include details such as the estimated
length, material designation, insulation and coating requirements and
reference drawings. Some level of complexity can be assigned to the
length to account for miscellaneous fittings and related variables in
the cost estimate.
Finally, orthographic and isometric piping drawings should indicate the
piping, fittings, valves, material, weld and testing requirements that
pertain to the tie-in. Often, the tie-in references are deleted from the
"as-built drawings" at the close-out phase of the project.
Design considerations
The plant and process considerations are usually obvious. Immediate or
projected increases in utility or process flow rates are the most
frequently cited reasons for tie-in piping. Accommodating the need for
these increased demands often results in additional capital equipment.
After the process requirements are determined and the tie-in piping
sized, consider isolation provisions. It is rarely feasible economically
to shut down the plant or process during tie-in piping installation.
Alternately, a short-term, scheduled outage may be sufficient to break
the line and install a tie-in connection. After the connection is in
place, the piping can be fabricated and connected "off-line"
conveniently and economically.
During the interim period, a blind flange can be installed and the
process resumed. However, this will require another brief outage to
remove the blind flange and connect the tie-in piping. This can be
avoided by installing a shutoff valve upstream of the blind flange to
provide safe, long-term isolation. Subsequently, the blind flange can be
removed, the connecting pipe installed, and the valve opened after the
tie-in is completed.
Pay particular attention to installing a shutoff valve that is adequate for temporary "end-of-line service" by considering these factors:
-Valve seals must withstand full rated pressure on one side while
unpressurized on the other side in the closed position.
-Valves must withstand a pressure and leak test.
-Valves must be bidirectional so they can be installed with either end
open to atmosphere.
-Valves must be installed with a lockout device and comply with OSHA
Zero Energy requirements.
-The pressure drops across a tie-in valve (in the fully opened position)
should not be excessive.
-Provide a "drainable spool piece" downstream of the shutoff valve.
Continued at:
<a href="http://www.plantservices.com/Web_First/PS.nsf/Contents/862568C9007175818">http://www.plantservices.com/Web_First/PS.nsf/Contents/862568C9007175818</a>
6256923007C6E57?OpenDocument
Received on Mon Jan 01 15:47:00 2001
This archive was generated by hypermail 2.1.8 : Tue Mar 04 2008 - 11:40:09 EST