I've been told a hot tap on a PWHT Amine Gas (vapor) Line could be
accomplished and meet the stress relieving requirements with the
right welding procedures. This line is 12" sch 40 A106,GR B line with
an 8" Hot Tap connection required. We can't take a shutdown and we
can't find a spare valve or section to isolate and stay on line.
I need to know if anyone has had any experience with this situation. All I need to know is can it be done?
The Line is in an interconnecting pipe in a major Oil Rfinery built to B31 Codes in the United States.
Thanks Received on Tue Nov 26 19:43:00 2002