One thing missing from your check list is a P&ID check. The P7ID is the
fundamental design document . Hence for QA close out the lead designer should
walk every line and ensure that the installation complies with the design
intent.
--- JAVEEDI@iocl.co.in wrote:
Yes; you are right. We follow 2 types of checklists; one is for mechanical
completion (normally referred to as Punch-list) and other before
commissioning of a plant. The punch-list for Piping Mech. Completion is
prepared by contractor and checked by Project Management Consultant (PMC)/
Owner; to be liquidated by Contractor. The checklist before commissioning is
by Client Operations/ other groups/ PMC and the completion of systems is
recorded over a few designated 'Handover' formats. It is highly desired
that the total piping be got checked from Mechanical/ Process/ Operations/
Instrument viewpoint.
Some of the general points of check wrt Isometric/ GA drawings are:
Supports check
Welding of Joints, slag removal etc.
Valves, location & their direction wherever applicable
Venturi/ instruments/ orifices/ other fittings;
Pipe condition (say dents/ pitting etc if at all)
Drains/ vents
Special notes with respect to P&IDs
Specific checkpoints related to special piping such as Slopes, Jacketing
connections etc.
Piping completion including branching etc wrt drawings/ General
arrangements.
Regards,
-----Original Message-----
From: tomcruz55 [mailto:tomcruz55@yahoo.com]
Sent: Wednesday, March 26, 2003 11:37 PM
To: PipingDesign@yahoogroups.com
Subject: [PipingDesign] Re: Feild Check List
The pdf file referred to below is all about pipe modeling. A field
checklist prior to commissioning or mechanical acceptance is normally
term as punchlist. Normally this is part of the project deliverables
prepared not by Owner but rather by the Contractor.
The norsok site may hve something on this. If not email me and I'll
send you a copy of our commissioning manual pertaining to Piping (if
i still have it - not sure)Normally this activity fall unders the
responsibility of your QC/QA (local law may require Inspector
signoff) and not Operation.
- In PipingDesign@yahoogroups.com, "Tom Boaz" <boazt@p...> wrote:
> http://www.pipingsolutions.com/triflex/whitepapers/wheredoistart.pdf
> ----- Original Message -----
> From: <empress4349@y...>
> To: <PipingDesign@yahoogroups.com>
> Sent: Tuesday, March 04, 2003 10:35 AM
> Subject: [PipingDesign] Feild Check List
>
>
> > Hello,
> >
> > Are there any field check list for piping available.. I'm looking
for
> > one to be recommended for the operator before startup.
> >
> > Thanks,
> > Ramachandran
> >
> >
> >
> > =====================================================
> > Discussion List sponsor: The fluid flow calculations website -
> www.LMNOeng.com - LMNO Engineering,
> > Research, and Software, Ltd.
> > =====================================================
> > unsubscribe: PipingDesign-unsubscribe@yahoogroups.com
> > =====================================================
> >
> >
> > Your use of Yahoo! Groups is subject to
http://docs.yahoo.com/info/terms/
> >
> >
> >
> >
Discussion List sponsor: The fluid flow calculations website -
www.LMNOeng.com - LMNO Engineering,
Research, and Software, Ltd.
unsubscribe: PipingDesign-unsubscribe@yahoogroups.com
Your use of Yahoo! Groups is subject to http://docs.yahoo.com/info/terms/
This electronic communication and any accompanying document is being
transmitted over the Indian Oil Network and contains confidential
information that is for the exclusive use of the individual or entity to
which it is addressed and is protected against unauthorised disclosure. If
the reader of this message is not the intended receipient or the employee or
agent responsible to deliver to the intended receipient, or is not intended
to act on it, be aware that any disclosure, dissemination, distribution or
copying of this communication, or the use of its contents is prohibited and
is likely to be attended by legal consequences. If you have received this
communication in error and/or are not the intended receipient, please
immediately notify the undersigned or Indian Oil Corporation Ltd. at the
telephone or the fax number or email address given above and permanently
delete the original message from your email system. Whilst this mail has
been checked for all the known viruses, recipients should undertake their
own virus checking as Indian Oil Corporation Ltd. will not accept any
liability whatsoever
Yahoo! Groups Sponsor ADVERTISEMENT
Discussion List sponsor: The fluid flow calculations website - www.LMNOeng.com
- LMNO Engineering,
Research, and Software, Ltd.
unsubscribe: PipingDesign-unsubscribe@yahoogroups.com
Your use of Yahoo! Groups is subject to the Yahoo! Terms of Service.
Design Detail and Development (a division of Blenray Pty Ltd)
We specialise in pipe network and waterhammer analysis, pipe stress analysis,
the design of buried pipelines and thermoplastic pipe systems.
Overseas tel 61 2 402 35 2313 fax 61 2 8850 2313 mobile 0402 35 2313
Mail Address PO Box 1351 Castle Hill NSW 1765 Australia
Do you Yahoo!?
Yahoo! Platinum - Watch CBS' NCAA March Madness, live on your desktop!
http://platinum.yahoo.com
Received on Thu Mar 27 15:44:00 2003