Dear colleague,
The query does not specify the job conditions, like,
the material of construction, service, operating
pressure, operating temperature, etc.
One probable reason could be the flexibility analysis.
The pipeline may appear to be perfectly OK after
undergoing all the prerequisites as the welding
procedure, physical examination and NDT checks, stress
relieving, cleaning and all that. The pipe supports
are to be executed as per the recommendations of the
stress engineer, and if possible, endorsed by him/her,
of course, if the line is to operate at a high
temperature. The slightest negligence in this matter,
as to provide the required gaps at guides, providing
the correct directional stops, proper fixation at the
anchors, the right placement of the spring hanger,
locking / unlocking of the spring, etc. can result in
unimaginable values of stress concentrations at
certain locations which ultimately can lead to
failure, when the hot process fluid is admitted into
it.
Well, you may check up this aspect of the line.
The other could be the MOC itself. The compatibility
of the material with respect to the service fluid may
once again be checked. It could be traced to corrosion
as well.
Please present the complete case study so that someone
could analyze it properly.