We use the term TOG (Top of grouting) to avoid such confusions.

Have a nice day.
-Mandar.
This message comes from Mandar's desk.

                       "Paul Bowers"
                       <pbowers@pipingd         To:     
<PipingDesign@yahoogroups.com>
                       esign.com>               cc:
                                                Subject: [PipingDesign] New at
Piping Design Central: Machinery
                       03/06/2004 06:08         Grouting
                       AM
                       Please respond
                       to PipingDesign






http://www.pipingdesign.com/pumps.html

Machinery Grouting
M&M Precision Grouting

<<Grout has to be used in conjunction with a properly torqued anchor bolt system when both static and dynamic loading is involved, such as with compressors, turbines, pumps, gear boxes and most heavy industrial machines. It takes both good grout and good bolts to properly hold the modern machines industry uses today.>>

This reminded me of the old "Top of Concrete" vs. "Underside of Baseplate" issue. T.O.C. used to be (and maybe still is) a common abbreviation on engineering drawings. But top of concrete is not important - what is important (for piping installations) is the actual elevation of the underside of the machinery's baseplate, because levelling grout exists between the top of concrete and the underside of baseplate. The thickness of the grout can vary. Anyone have any additional comments on this?

Quick sketch: http://www.pipingdesign.com/drawings/grout.jpg

Paul



PipingOffice - Excel Spreadsheets for Piping Calculations http://www.pipingoffice.us/

Main site: http://www.pipingdesign.com

Yahoo! Groups Links Received on Fri Mar 05 23:11:00 2004

This archive was generated by hypermail 2.1.8 : Mon Oct 27 2008 - 20:24:03 EDT