for simple task/manpower scheduling - the use of Primavera might be an
overkill. The learning curve isnt easy too and theyre not cheap
either. If youre looking for a software that will determine the
critical path,provide uou with an update, compare your actual againts
the baseline, track the activities, print the timeline/barchart then
MS Project will do the job.
MS Excel can also be setup actually to track work progress and do the barchart.