I've been following this thread for a while - Field fit up can be a cost saving or cost addition to a project.
Field Fit Up implies that a construction crew actually presents the
piping spool pieces, marks the Field Fit Up section - removes it , cuts
and bevels the section, re-presents the Field Fit Up section, and then
proceeds with the actual field welding.This can be a very a very man-hour
intensive procedure
The construction crew must perform the following steps - primary rigging
/ presentation / marking / derigging / cutting / beveling/ and rerigging
prior to actual field welding.
Example #1: replacement in kind of a 6" sch 40 cs piping section due to
corrosion. No Unit Shutdown
Designer has original drawings, isos, field verifies dimensions, and adds
FFW's because he didn't want to go up in the piperack and physically
verify the existing piping route
# of FFW's - 2
Designer time not spent to verify piperack dimensions: 20 manhours
Additional construction crew time to install piping system with 2 FFW's:
80 hours
Example #2 - replacement of a 12" sch.160 Incoloy piping system due to
metallurgical upgrade: Unit Shutdown
Designer has original drawings, isos, complete laser scanning has been
performed
Designer did no field verification of dimensions due to laser scanning -
# of FFW's - 0
Due to the confidence of laser scanning point clouds all spools were
"pre-fabbed", with only FW's called out, but during the subsequent unit
shutdown and installation there were numerous installation problems which
required modifications to the original spool pieces
Designer time to field verify dimensions - 0 manhours
Additional construction crew and engineering time to install system - 240
hours
Actual cost impact for lack of FFW's - 2 additional days of unit shutdown
@ $1,250,000 per day.
Important Comments on laser scanning - If you are working on a laser
scanning driven project don't forget the following:
1) Laser scanning only "sees" the outside surfaces of piping, if you have
an insulated line it will not be able to pinpoint actual pipeline center
lines.
2) Laser Scanning does not take into account piping "Shrinkage" due to
operating vs. shutdown temperature differentials, normally a laser scan is
performed while a unit is operating, but when the actual modification is
done the affected piping systems, and or equipment will be at ambient
temperature
If in doubt as to the utilization of FFW's consult with your supervisor, and also with your construction group - good planning and coordination / engagement of all involved groups normally will assist in making the proper decisions.
Bruce R. Raymond
Senior Design Supervisor
Fluor
Any views expressed in this message are those of the individual sender and may not necessarily reflect the views of the company.
[Non-text portions of this message have been removed] Received on Mon Jul 28 06:53:00 2008
This archive was generated by hypermail 2.1.8 : Tue Mar 09 2010 - 00:21:27 EST